Transformer Services
The frequency of testing and maintenance of transformers varies depending on the condition
of service and the atmosphere in which it operates. In general, a thorough energized
inspection, including liquid analysis, fault-gas analysis and infra-red inspection should
be performed at least annually.
Transformer inspection, testing and
maintenance can be divided into two general categories, work that can be performed when
equipment is
|

 |
|
Testing while
Transformers are Energized
-
Visual Inspection
HVM technicians look for cleanliness, cracked insulators and bushings,
condition of paint, oil levels, oil leaks, oil/winding temperature gauges, nitrogen pressures, relay targets,
condition of grounds, etc.
-
Infrared Inspection Using the latest state of the art infrared cameras projecting high-resolution thermal
images, HVM technicians are able to locate hot spots, poor connections, defective surge
arresters, etc. The inspection is fast, accurate and practical. It is also recommended by
ANSI/NFPA 70B.
-
Corona Detection Excessive corona produces RF interference and may cause an insulator, bushing or surge
arrester to fail. Using an ultrasonic corona detector, HVM can identify improperly shaped
medium and high voltage connections, defective insulation, bushings, and surge arresters
all likely causes of excessive corona.
-
Nitrogen Gas Tests On nitrogen gas blanketed transformers, gas samples are extracted and two tests are
performed:
-
Percent TCG: Most transformer failures
are caused by incipient defects such as hot spots or overloading. These defects create
combustible gas and their detection calls for more in-depth gas-in-oil analysis.
-
Percent Oxygen: High oxygen content in
a transformer may indicate "wet" atmosphere has entered the transformer. Oxygen
also accelerates the deterioration of oil.
-
Oil Analysis When transformer oil deteriorates, sludge ultimately forms and coats the windings,
resulting in decreased cooling capacity and degradation of the solid insulation system.
Some of the oil analysis tests include:
Measuring specific combustible gas
levels in transformer oil is a good way to predict transformer problems. HVM technicians
and engineers compare the results of historical records to recent test results as
precursors of internal problems such as arcing, corona and overheating.
Testing while Transformers are
De-Energized
Testing these transformers is similar to test
procedures for liquid-filled transformers in that de-energized inspection and testing is
required. Corrective maintenance for severe leaks, bushing replacement or any other task
that requires opening up the unit is more complex, because special equipment and
procedures are required which involve removing, storing and replacing the gas in the
transformer.
Open or ventilated transformers are tested
routinely when de-energized by internal inspection. Since the core and coils of these
units are subject to contamination by air flowing through the transformer, maintenance
includes cleaning the internal parts. Also, since the voltage impulse levels for dry-type
transformers are usually lower than for liquid filled transformers, surge arrestors are
often installed either inside the transformer case or immediately adjacent to it. Whenever
de-energized maintenance is performed on the transformer, the arrestors should be
inspected, cleaned and tested.
|